New Year, New Construction Progress at The Junction

We’ve hit the ground running in 2023, with our construction team back on site and hard at working bringing our community to life!

03 Feb 2023

Work on the final three stages at The Junction is back up and running, with footpaths and final topsoiling of lots set to be completed shortly for Stage 4. That means Practical Completion is just around the corner and we will be requesting Statement of Compliance from all authorities in the coming weeks!

In other news, over in Stage 5, watermains are being installed and kerbs are being poured.

And finally for Stage 6, base course asphalt is being completed this week, with watermain installation to commence shortly after.

We’ll be sure to keep you informed of all the latest progress at The Junction as we continue 2023. And in the meantime, be sure to visit the MyJunction portal so you can keep an eye on the progress of your land in real time!

Stage 4
Stage 5
Stage 6
Back to blog