That’s a Wrap on 2022 – The Junction’s Construction News
It seems like the year has gone by in a flash, with plenty happening on site as our team works hard to make our community a reality!
Progress on the final three stages in our community is finishing strong this festive season, with Road Boxing, Kerb & Channel, as well as Electrical and Communication reticulation works now complete for Stage 4. Footpaths are also nearing completion.
Over in Stage 5, agricultural drains and conduits are now complete, as is Road Boxing, with Kerb & Channel to commence in the New Year.
And finally for Stage 6, Road Boxing and Kerb is complete, while retaining walls and water reticulation works are set to commence shortly. Base Course Asphalt will be laid in the New Year.
As we wrap up 2022, we’d like to take this opportunity to thank all our current and future residents for their patience and wish everyone a safe and Merry Christmas. We’re looking forward to an exciting 2023 at The Junction!
Our sales team will be taking a short break, returning on Saturday 7th January 2023. During this time, we will be available via phone on 0497 111 722 if you have any enquiries or register your details here and one of our team will get back to you upon their return.
We’ll be sure to keep you informed of all the latest progress at The Junction in the New Year. And in the meantime, be sure to visit the MyJunction portal so you can keep an eye on the progress of your land in real time!