The Junction November Construction Update

The end of 2022 is in sight, and our team is working hard to see out the year in style – working hard across the estate!

25 Nov 2022

It has continued to be a month of wild weather across Melbourne, but our construction team has been doing their very best to progress the final three stages at The Junction.

We’re pleased to report that base course asphalt is now complete for Stage 4. Electrical reticulation is underway and street lighting is being prepped for installation.

As for Stage 5, agricultural drains and conduits are currently being constructed, while retaining walls and water reticulation will be commencing shortly for Stage 6.

We’ll be sure to keep you informed of all the latest progress at The Junction on our Facebook and Instagram pages. And in the meantime, be sure to visit the MyJunction portal so you can keep an eye on the progress of your land in real time!