The Latest Construction News at The Junction

The end of 2022 is in sight, and our team is working hard to see out the year in style – working hard across the estate!

28 Oct 2022

Despite some very wet weather of late, our construction team has been doing their very best to progress the final three stages at The Junction.

We’re pleased to report that kerb construction for the internal roads and intersection is now complete in Stage 4. Asphalting of these roads will be completed in the next fortnight, which is exciting news for residents! Next up will be electrical reticulation works, which are scheduled to commence in early November.

And finally, Sewer and Drainage works are also complete for Stages 5 and 6, with Boxing of internal roads also nearing completion.

We’ll be sure to keep you informed of all the latest progress at The Junction on our Facebook and Instagram pages. And in the meantime, be sure to visit the MyJunction portal so you can keep an eye on the progress of your land in real time!